In August 2019, MOB started with their activities for a mechanical and piping project at the Chemelot industrial area in Geleen. 

A complex and challenging project We had a tight deadline to meet. In record time, an expert project team was pulled together from The Netherlands and Belgium. Our project team needed to ensure not only that the inventory-taking was performed faultlessly, but also that the installation of the materials required and the delivery of the project itself was optimal. Our project team has installed pipes and pumps and has reviewed all current work activities. The project had a high complexity because we’ve had to work with very thin piping materials. Therefore, our welders needed extra qualifications to get the job done. 

At first, we thought that 16.000 man hours were enough to complete the project, but eventually we’ve spend over 30.000 man hours. Despite of the high complexity, we’ve completed this project safely, on time and to the client’s satisfaction.