In early 2010, fabricom/gdf suez commissioned mob for pipeline activities in the construction of the sita reenergy industrial waste incineration installation (dutch: baviro).

MOB Netherlands and Belgium worked together on the thermal part of the installation, the prefabrication and installation of the pipelines, and the connections of these parts to the new incinerators. The project was completed in the autumn of 2010 and had required approximately 40,000 man-hours.

SITA ReEnergy invested €180m in the new installation in Roosendaal and which has an annual waste processing capacity of 291,000 tonnes. The energy generated during incineration can provide power to 70,000 households and 49% of this is considered green energy.

More information: www.baviro.nl
New waste incineration  installation  for baviro